Milestone Payment Overdue: What to Do and What You Can Claim

If a milestone payment is overdue, first confirm from your contract that the milestone trigger has really been met and the payment date has really passed. Then chase in writing, add statutory interest and fixed compensation where the Late Payment Act applies, and escalate if the client goes quiet. This guide covers each step for UK businesses, from a first reminder to adjudication, a statutory demand and specialist collection.

Debtrecoveryhub
Get Help Recovering Overdue Payments
Debtrecoveryhub matches businesses with vetted collection agencies based on debt type, amount, age and location.

Find a collection agency

TL;DR

  • Check the trigger first: the contract decides when a milestone is due, and in a construction contract the Construction Act sets minimum rules for due dates and final dates for payment.
  • Chase in an escalating, documented order: friendly reminder, formal late-payment notice, final demand, then a letter before action.
  • For a qualifying business-to-business debt you can claim statutory interest plus fixed compensation of £40, £70 or £100, depending on the size of the debt.
  • Suspending work is a real lever, but in construction it needs seven days’ written notice, and elsewhere it depends on your contract wording.
  • Escalate on a pattern (broken promises, silence, shifting excuses), not on a single missed date.

Table of Contents

First, is the milestone payment really overdue?

Most disputes about overdue milestones are not about the money. They are about whether the money was due yet. Before you send anything with the word “overdue” in it, check four things in the contract.

1. The trigger event. What exactly makes the milestone payable: completion of a deliverable, a sign-off, a certificate, a date? Travers Smith advises checking the trigger, whether a valid invoice is needed, and when the credit period starts, which is typically on invoice issue or receipt.

2. Whether sign-off is a condition. Clients sometimes hold back a milestone by not signing off. In Bennett (Construction) Ltd v CMC MBS Ltd, the Court of Appeal looked at sign-off objectively: payment became due once the work had reached the state in which it was capable of being signed off, so a signature or certificate was not necessarily required. That case concerned a construction contract, so read your own wording and take advice before relying on it.

3. Whether the contract is entire or divisible. Under an entire contract, payment may not be due until all obligations are discharged. If your milestones are meant to be separate instalments, the contract should say so clearly.

4. The payment period. If you agreed a payment date, that is your date. GOV.UK explains that an agreed date should usually fall within 60 days unless a longer period is fair to both businesses. If no date was agreed, payment is late 30 days after the customer receives the invoice, or after delivery of the goods or service if that is later.

Extra rules if it is a construction contract

The Housing Grants, Construction and Regeneration Act 1996 (the Construction Act) adds protection. Under section 109, a party is entitled to instalment, stage or periodic payments unless the contract says the work will last less than 45 days. Under section 110, the contract must contain an adequate mechanism for working out what becomes due and when, plus a final date for payment.

If your milestone mechanism does not meet that standard, the Scheme for Construction Contracts fills the gap. Per the same Fenwick Elliott analysis, paragraph 7 of Part II makes an other payment due seven days after completion of the relevant work or when you make a claim, whichever is later.

Then section 111 bites: the payer must pay the notified sum by the final date for payment unless they have served a valid notice to pay less, which must state the sum they consider due and how it was calculated. A client who missed that notice deadline has a weak position if they simply withhold.

Find out why it has not been paid

Before escalating, work out which of three situations you are in: an administrative hold-up, a genuine dispute, or financial difficulty. DueSparrow suggests a root-cause check before escalation, and it changes your tone.

  • Administrative: the invoice went to the wrong person, lacks a purchase order number, or missed the client’s payment run. Fix the paperwork and ask for a payment date.
  • Dispute: the client says the work is incomplete or defective. Ask for the specifics in writing and respond to each point. Ashfords notes that payment problems can often be resolved quickly by addressing the client’s concerns and supplying missing information.
  • Financial difficulty: vague promises, new contacts each time, partial payments. Speed matters more here, because every week lets other creditors move ahead of you.

A short phone call often settles which one it is. Follow it with an email that records what was said.

A sensible order for chasing

The approach that holds up best, if the matter ever reaches a court or an agency, is one with a clear paper trail. Sirion’s escalation guidance describes a documented, escalating approach: a friendly reminder, a formal notice of late payment, a final demand, then legal or third-party collection, keeping all correspondence and contract records throughout.

  1. Day one after the due date: friendly reminder. Quote the milestone, the invoice number, the amount and the due date. Attach the invoice again.
  2. Within a week: formal late-payment notice. Cite the contract clause, state the amount outstanding and, if your terms say so, that you will charge statutory interest and compensation.
  3. Final demand. Give a short, firm deadline (seven to fourteen days is common practice) and say what you will do next if it passes.
  4. Letter before action. Set out the debt, the legal basis and the step you will take, whether that is adjudication, court proceedings or a statutory demand.

Keep every step in writing, even after phone calls. If you want a fuller walk-through, our debt collection checklist for UK businesses and the guide to recovering unpaid invoices cover the same ground with templates in mind.

Statutory interest and fixed compensation

If your client is a business and you are supplying goods or services, you may be able to charge statutory interest under the Late Payment of Commercial Debts (Interest) Act 1998. Interest starts the day after the relevant day: where a payment date is agreed, that date normally applies, and without one it is the later of performance or the purchaser receiving notice of the amount, plus 30 days.

GOV.UK states that the statutory rate is 8% above the Bank of England base rate. It is simple interest. Brentwood Council’s worked method is the debt, multiplied by the rate, divided by 365, multiplied by the days late.

On top of interest, section 5A of the Act gives you fixed-sum compensation for recovery costs, and reasonable costs above that sum:

Size of the debt Fixed compensation
Under £1,000 £40
£1,000 to £9,999.99 £70
£10,000 or more £100

A worked example: a £12,000 milestone is 20 days late, and the base rate is 4% (an illustrative figure only: use the current rate). The rate is 12%, so interest is £12,000 × 12% ÷ 365 × 20, about £78.90, plus £100 compensation. Modest, but it adds weight to the demand, and it grows daily.

Two more points. Contract terms that exclude statutory interest are void unless they provide a substantial contractual remedy, so a client cannot casually contract out. And you are better placed if your own terms mention the right: see our guides on late payment interest wording, Late Payment Act interest and late payment compensation.

Statutory interest and fixed compensation — overview diagram

Can you pause work?

Suspension is the lever that gets finance teams moving, and it needs care.

In a construction contract, section 112 of the 1996 Act lets a person owed a sum suspend performance if it is not paid in full by the final date for payment and no effective notice to pay less was given. You must give at least seven days’ notice of your intention, stating the grounds. Payers can only reduce what they pay by serving a notice of intention to pay less specifying the sum and the basis, within the prescribed period.

Outside construction, there is no equivalent statutory right in what we have reviewed, so your contract is everything. A good clause says that if a milestone payment is overdue, you may give written notice and pause work until it is paid, and that deadlines move accordingly. If your contract is silent, take legal advice before stopping work: suspending without a right to do so can put you in breach.

Whatever your sector, write the clause before you need it. Make milestones depend on outcomes the client can see, not on internal effort, as ClearTimeline recommends, and define the triggers in writing.

Our perspective

We see the same pattern in overdue milestone cases: the money is rarely lost because of the debtor’s first refusal. It is lost because the creditor’s paperwork was thin when the matter finally had to be proved. A vague trigger, an invoice sent to the wrong person, no record of the reminder. The strongest cases look boring: a clear clause, one dated invoice, a polite trail of escalating letters.

We also think escalation should follow behaviour, not the calendar. One missed date from a client who answers the phone is a conversation. A client who stops engaging, breaks promises or invents new reasons each time is a different matter, and is the point to bring in someone who does this daily. That matches the view of Ledingham Chalmers, who describe escalation as driven by a pattern showing routine credit control is no longer working.

Our role is the matching step. Rather than searching blind for an agency, you give us the debt type, amount, age and location, and we point you to vetted agencies that handle cases like yours.

— Jack

If the client still refuses to pay

When reminders and a formal demand fail, you have several routes. Which one fits depends on whether the debt is disputed.

  • Letter before action. It sets out the claim and a final deadline, and it is expected before court proceedings.
  • Adjudication. For construction contracts, Ashfords advises taking professional advice on adjudication, which can be particularly useful where the payer failed to issue the right notices in time.
  • Statutory demand. Ashfords also points to a statutory demand for an undisputed debt. It is a serious step with insolvency consequences for the debtor, so do not use it where the debt is genuinely contested; speak to a solicitor first.
  • Court claim and enforcement. After judgment, common enforcement methods include High Court Enforcement Officers, charging orders and winding-up petitions.

If you also need a view on timing, our guide to UK debt collection timelines explains when each escalation usually makes sense.

When to bring in a collection specialist

Rezolva’s UK guide suggests specialist collection once the debt is overdue, the documents and debtor details are checked, ordinary reminders have failed and any genuine dispute has been identified. Broken promises, avoidance, cash-flow strain or a deteriorating debtor can justify moving sooner. If a high-value account is involved, take legal advice after your own documented outreach.

When the client is overseas

Cross-border milestones add two problems: which law applies, and where you can enforce.

On the first, choosing English law is not always enough for the Late Payment Act to apply. According to CMS, the Act applies only if there is a significant connection to the UK or the contract would be governed by UK law apart from the parties’ choice.

On the second, enforcement may mean working with foreign lawyers, either to enforce an English judgment abroad or a foreign one here, as Boyes Turner notes. English courts have also shown willingness to use tools such as third-party debt orders to support international trade outcomes.

For the practical routes, see our guides to international debt recovery in the UK and enforcing a foreign judgment.

Getting matched with a collection agency

If your overdue milestone has moved beyond reminders, we can help you find the right specialist without the guesswork. After a detailed intake covering the type, size and age of the debt and where the debtor is, we recommend vetted agencies suited to the case. You do not pay us for the introduction. Start with our business debt recovery page, or tell us about your case.

Preventing the next overdue milestone

Most of what helps is done before the work starts.

  • Tie each milestone to an outcome the client can see and verify, and state the evidence that proves it.
  • Say whether sign-off is required, who gives it, and what happens if the client does not respond within a set number of days.
  • State the payment period and when it starts running (invoice issue or receipt).
  • Include a right to pause work after written notice if payment is late, and a clause on statutory interest and compensation.
  • Name an accounts contact and note the client’s processing requirements, such as purchase order numbers, so the invoice is not rejected on a technicality.

FAQ

What happens if a payment is overdue?

The payer is in breach of the payment term, and for a qualifying business debt you may charge statutory interest and fixed compensation. You should chase in writing, and escalate to a formal demand and legal or agency action if the debt remains unpaid and is not genuinely disputed.

Can I charge interest on an overdue milestone payment?

Yes, if the Late Payment of Commercial Debts (Interest) Act 1998 applies, which in general covers business-to-business supplies of goods and services. Interest runs from the day after the relevant day, and you can add fixed compensation of £40, £70 or £100 depending on the debt.

Can I stop work if the client has not paid a milestone?

In a construction contract, you can suspend after giving at least seven days’ written notice, if the sum is unpaid by the final date and no valid pay-less notice was served. In other contracts it depends on your wording, so check it or take advice before downing tools.

When should I hand an overdue milestone to a debt collection agency?

Once your documents are checked, reminders have failed and any real dispute has been identified. Silence, broken promises or signs of financial trouble justify going sooner.

Sources