If your retention was due for release and has not arrived, start with the contract. Find the release trigger, work out the sum and the date it fell due, then send a written demand that names the breach and reserves your rights. If that fails, adjudication or a court claim is the usual next step. Below we explain how to do each of these, what to do when the payer cites defects, and where the planned retention ban stands.
Retention is a specified percentage deducted from the sums due to a contractor by way of interim payment. It is held as security for due performance, or as a fund to complete the work or rectify defects if the contractor fails to do so. A government-commissioned report by Pye Tait describes it in similar terms: a percentage of the contract value withheld to protect against non-completion or defects and to encourage remedial work.
In practice, a retention is usually a small percentage, around 3 to 5%, of each interim payment and is held until the end of the defects period. We have not linked a source for that range beyond the general description above, so check your own contract for the actual figure. What matters is this: the money is yours, and it is only being held. Once the trigger in your contract has been met, it stops being security and becomes a sum owed.
Retention is unpaid in two typical situations:
The route to recovery is similar for both. The evidence you need differs.
This is one of the most common questions, and the answer is: proposed, not yet in force for your current claim. The government’s Commercial Payments Bill overview of 19 May 2026 proposes prohibiting the deduction and withholding of retention payments under construction contracts. It says the timing of implementation is still to be consulted on.
The detail in the Bill’s own documents matters for anyone with money held right now. It proposes a transition period for retention clauses agreed in the two years before the ban comes into force, the return of remaining retained sums before that period ends, and a fixed sum payable for unauthorised retention deductions. The Small Business Commissioner repeated the two-year transition and fixed-sum points in a second-reading speech on 10 June 2026, and cited industry estimates of around £223 million of retention lost each year to insolvency, with £4 billion to £6 billion held across the industry at any time.
Earlier, the January 2026 policy annex described two options: prohibition, or protecting deducted retention funds against insolvency and late or non-payment. The Small Business Commissioner’s own page says the proposals may change before they become law.
What this means for you:
There is no single answer, and that is the root of many disputes. UK statute and common law impose no universal maximum period for withholding retention. The contract controls, and it commonly provides for staged release: part at practical completion, the balance after the defects period.
Some benchmarks help you judge whether what you are being told is reasonable:
These are public-sector or standard-form models, not rules for your private subcontract. They are useful as a yardstick when a payer’s holding period looks disproportionate.
One point protects subcontractors in particular. For contracts entered into after 1 October 2011, the Pye Tait report records that release of subcontract retention cannot be linked to an event under another contract. The subcontract must contain its own release trigger. If your payer says it is waiting for something under the main contract, check this first.

The recovery sequence below follows professional guidance on recovering retention. Work through it in order. Each step strengthens the next.

Find five things: the retention percentage, the release trigger or triggers, the payment and pay-less notice provisions, any late payment terms, and the dispute procedure. Check amendments and variations too. Many retention fights are won or lost on a single clause.
Work out exactly how much is held and when each portion fell due. A precise figure, with the arithmetic shown, is harder to dispute than a vague claim. If your terms include late payment provisions, note them. On overdue invoices generally, our guide to statutory interest on late payments explains what you may be able to add.
The letter should identify the contractual breach, state the sum and the date it was due, set a short deadline and reserve your rights. Keep it factual. Do not threaten anything you will not do. Send it by a method that proves delivery and copy the person named in the contract’s notice clause.
See the checklist in the next section. Gather it now, before the dispute hardens, because people leave projects and email accounts get tidied.
If the demand fails, consider the contract’s dispute mechanism: adjudication, arbitration or court proceedings. We cover the choice below.
CLC guidance stresses that contemporaneous records and a clear contractual and cost case are central to recovery. Its dispute-resolution material says strong contemporaneous records improve negotiation and tribunal outcomes, while unsupported global assertions are likely to fail. Aim for a file that a stranger could follow in ten minutes.
| Document | What it proves |
|---|---|
| Executed contract and amendments | The retention percentage, release trigger and dispute route |
| Payment applications and valuations | What was certified and what was deducted |
| Payment and pay-less notices | Whether the payer followed the contractual process |
| Certificates (completion, defects) | That the release trigger has been met |
| Defect notices and your responses | Whether defects were raised, and whether you dealt with them |
| Invoices and ledger entries | The amount due and the amount outstanding |
| Correspondence and demands | Your chasing history and the payer’s stated reasons |
| Proof of non-payment | That the money has not arrived |
For a broader view of what a creditor should keep, see our page on evidence for unpaid business debt.
Many unpaid retentions are not simple oversight. The payer says the work is defective, or that it is waiting for a payment from further up the chain. RICS notes that cash retention is easy to calculate but generates disputes when held longer than stipulated or in amounts disproportionate to the remaining defects.
Professional guidance suggests this approach:
A useful test: if the payer is holding 100% of the retention against a single minor snag, ask why the held sum is proportionate to the cost of putting it right.
The same logic applies to clauses that tie your payment to the payer being paid. Our guide to pay-when-paid clauses explains how to read them.
An unpaid retention can generally be pursued through the contract’s dispute mechanism. Where the statutory construction adjudication regime applies, that includes adjudication, with court enforcement or a substantive court claim where appropriate.
A short comparison of the usual routes:
| Route | Where it tends to fit |
|---|---|
| Negotiation after a formal demand | Clear-cut overdue sums, payer still solvent and engaged |
| Adjudication | Construction contracts within the statutory regime, where you want a quick decision on a defined dispute |
| Arbitration | Where the contract requires it |
| Court claim | Where the contract allows it or you need a judgment, including enforcing an adjudicator’s decision |
Take legal advice from a construction solicitor before starting adjudication. Whether the statutory regime applies to your contract, and how the dispute is framed, can decide the outcome. Costs are also a live question: our page on recovering legal costs on unpaid business debt sets out what you can and cannot usually claim back.
If the payer is insolvent, the picture changes. Subcontractors with unpaid retention are typically unsecured creditors, so speed matters. Contact an insolvency practitioner or solicitor as soon as you hear of financial trouble, and read our overview of construction debt recovery for UK contractors.
Retention ties up working capital for months or years. Some firms smooth the gap with finance, such as a revolving credit facility secured against a property portfolio, though that suits only businesses with suitable assets. Others negotiate a retention bond or guarantee in place of cash. CLC and NEC guidance identifies performance bonds, parent-company guarantees and retention bonds as possible alternatives to cash retention. Raise that before you sign, not after the money is stuck.
Retention payments get no special treatment under the Construction Industry Scheme. HMRC says they are treated like other payments, and whether deduction or gross payment applies depends on the subcontractor’s status when the retention is paid. If your status has changed since the work was done, speak to your accountant before you invoice.
We see the same pattern again and again with trade and construction debts. The money is rarely lost because the claim is weak. It is lost because the claimant waited, kept thin records, or chased in a way that gave the payer no clear deadline. Retention makes this worse, because the debt sits quietly for a year or more and the people who agreed it move on.
Our advice is to treat the release date as a diary entry, not a hope. Calendar the trigger on the day you sign. When it passes, send the demand within days, not months. Keep your file as if you will be in front of an adjudicator, because many of the cases that reach a collection specialist already are heading that way.
We also think the choice of help matters. A collector who does not understand construction contracts will chase the wrong sum, or push a disputed claim as though it were a plain overdue invoice. That is why we match each case to an independent agency on the details: debt type, amount, age and location. Sending one case to a generalist at random is the avoidable mistake.
— Jack
If a demand has not worked and you would rather not manage the chase yourself, Debtrecoveryhub can help. You give us the details of the debt, its size, its age and where the debtor is based, and we introduce you to a vetted independent collection agency suited to the case. You do not pay us for the introduction. See our business debt recovery service to start, or our guide to recovering unpaid invoices if you want to try the in-house route first.
Check your contract for the release trigger, calculate the sum and due date, and send a written demand that names the breach and reserves your rights. Gather your applications, certificates, notices and correspondence. If the payer still does not pay, consider adjudication, arbitration or a court claim.
There is no universal statutory maximum. The contract controls the period, often with part released at practical completion and the rest after a defects period. Public-sector models often use around 12 months for that defects period, but your own contract is what counts.
A ban has been proposed. The government’s Commercial Payments Bill overview would prohibit withholding retention under construction contracts, but implementation timing is still to be consulted on and details may change. Until a ban is in force, your existing contract governs.
It is a percentage of each payment held back by the paying party as security that the work will be completed and any defects put right. It is released in stages, usually at practical completion and at the end of the defects period, as the contract provides.